How Long Does Hardwood Floor Installation Take? A Step-by-Step Timeline
For most homes, plan on about one to two weeks from the day the wood is delivered to the day the rooms are back in use. If you are asking how long does hardwood floor installation take, the laying of the boards is the short part: often two to five days, depending on square footage. Acclimation before it, and sanding and finishing after it when the wood is unfinished, account for the rest.
This guide follows the job stage by stage, explains what adds days, and shows how to get the house ready so the schedule holds.
What are the stages of a hardwood floor installation?
A hardwood floor installation timeline has the same stages on almost every job. DNH Hardwood Flooring LLC publishes its own process on its Raleigh flooring contractor page, and it follows this order.
- On-site assessment: an in-home visit to look at the space, take measurements and define what the project needs
- Delivery and acclimation: solid wood is delivered to the home three days before installation so it adapts to indoor humidity
- Preparation: the site and the subfloor are made ready
- Installation: the planks are installed over two to five days, depending on square footage
- Sanding and finishing: added when raw, unfinished wood is selected
- Final walkthrough: the finished floor is reviewed with the homeowner
The site also states the payment schedule: a 50 percent deposit when materials are delivered and the remaining 50 percent after the homeowner inspects and approves the completed work.
Why does the wood have to sit in the house first?
Because wood changes size with humidity, and it needs to reach the conditions of the home before it is nailed down. Boards installed straight off the truck can shrink and leave gaps, or swell and cup, once they settle.
Hardwood acclimation time depends on the product and the season. DNH states that it stores materials inside the home for at least 72 hours before installation. During those days the heating or cooling should run as it normally does, and the boxes should stay in the rooms where the floor will go, not in a garage. A contractor can confirm readiness by comparing moisture readings of the flooring and the subfloor.
What can make the installation take longer?
Anything that adds preparation, complicates the layout or interrupts the sequence. Most delays are found in the first two days, when the old floor comes up.
- Removing existing flooring, especially glued-down material or tile
- Subfloor repairs: leveling, fixing squeaks, replacing damaged sections
- Moisture readings that are too high to install safely
- Stairs, which are slow, detailed work
- Patterns such as herringbone, borders or many small rooms and closets
- Weaving new boards into an existing hardwood floor
- Backordered material or trim
- Other trades working in the same rooms
The site describes subfloor preparation as leveling, cleaning and securing the underlayment for a squeak-free base. Time spent there is not wasted: problems under the boards are far harder to correct later.
Does prefinished or site-finished hardwood take longer?
Site-finished hardwood takes longer, because the floor is sanded, stained and coated in the house after it is installed. Prefinished boards arrive with the finish already applied at the factory, so the floor is usable soon after the last board and the trim are in.
The choice between prefinished vs site finished hardwood is not only about time.
- Prefinished: faster, little odor, very hard factory finish, small bevels between boards
- Site finished: a flat, continuous surface, any stain color, and an exact match to existing floors, at the cost of several extra days for sanding, coats and drying
Finish type matters too. Water-based finishes dry faster between coats than oil-based ones. DNH says on its site that it uses water-based traffic finishes with quick drying times.
How should you prepare the house?
Clear the rooms and settle the decisions before the crew arrives. Knowing how to prepare for hardwood floor installation is the part of the schedule a homeowner controls.
- Move furniture, rugs and breakables out, or agree in writing who will move them
- Empty closets that are getting new flooring
- Decide on stain color and sheen before the start date, using samples on your own wood if possible
- Plan for appliances, toilets or doors that have to be removed and reset
- Ask whether baseboards and shoe molding will be removed, reused or replaced
- Arrange where pets and children will be during noisy and coating days
- Keep the thermostat at normal living settings from delivery onward
- Clear a path and a parking spot for material and equipment
When can you walk on the new floor and move back in?
With prefinished wood, usually as soon as the installation and trim are complete. With a site-applied finish, it depends on the product. As a typical guide for water-based finishes, light foot traffic in socks is often possible about a day after the last coat, furniture can go back after a few days, and rugs should wait a couple of weeks while the finish cures. Follow the times your contractor gives, since they come from the product label.
Use felt pads under furniture and lift pieces instead of dragging them. The full list of what the company installs, including solid hardwood, laminate and luxury vinyl plank, is on its flooring services page.
Frequently asked questions about hardwood floor installation time
Can I stay in the house during hardwood floor installation?
Usually, yes, if the work is done in sections and you have a path to a bathroom, a bedroom and the kitchen. During sanding and coating days it is more practical to stay out of the affected rooms. Ask how the work will be phased.
How long does it take to install hardwood in one room?
A single, simple room is often laid in a day or two once the wood has acclimated. Preparation of the subfloor and any site finishing are added to that.
Can hardwood be installed in any season?
Yes, as long as the home is closed in and the heating and cooling are running. Acclimation and moisture checks matter in every season, and more so in humid summers.
Do I need to remove the baseboards?
It depends on the flooring thickness and the look you want. Baseboards can be removed and reinstalled, or left in place with a shoe molding added to cover the expansion gap. Decide this before the job starts because it affects painting.
Why is an expansion gap left around the room?
Wood expands and contracts with humidity through the year. A small gap at the walls gives the floor room to move without buckling, and the baseboard or shoe molding hides it.
Plan your installation with DNH Hardwood Flooring LLC
DNH Hardwood Flooring LLC is a family-owned flooring contractor founded in 2018 in Durham, NC. It installs, repairs and refinishes floors in Durham, Raleigh, Chapel Hill, Cary, Apex, Holly Springs, Wake Forest and Clayton. To get a schedule for your own project, call 919-225-9420 or contact DNH Hardwood Flooring LLC for a free on-site estimate.